Decision Log vs RAID Log: What's the Difference?
Kalpataru Sahoo ·
Both turn up in the same project folder, and both are called “logs”, but they do different jobs. One answers “what did we decide, and why?”. The other answers “what could stop us, and what are we doing about it?”.
Decision log vs RAID log at a glance
The simplest test: if the item is settled, it’s a decision. If it’s still uncertain or unresolved, it belongs in the RAID log.
| Aspect | Decision log | RAID log |
|---|---|---|
| Purpose | Keep a record of choices and the reasoning behind them. | Spot and manage what could derail the project. |
| What it records | Decisions already made. | Risks, assumptions, issues and dependencies: things still open. |
| Typical fields | Date, decision, rationale, alternatives considered, owner, status. | Type, description, likelihood and impact (for risks), owner, mitigation or action, due date, status. |
| Typical owner | Whoever made the decision; often the project lead or sponsor keeps the log. | The project manager keeps it; each item has its own owner. |
| Update frequency | When a decision is made. Entries rarely change afterwards. | Continuously. Reviewed in every status meeting. |
| Who reads it | Anyone asking “why is it like this?”, often months later. | The project team and steering group, every week. |
| Example entry | “Delay launch two weeks to finish payment testing.” | “Supplier may miss the 10 March delivery.” |
What is a decision log?
A decision log is a running list of the significant choices made on a project or in a business. Each entry records the decision, when it was made, who made it, and, most importantly, why. It exists for the moment, weeks or months later, when someone asks why things are the way they are and nobody remembers.
Typical fields: date, decision, rationale, alternatives considered, owner, status, and sometimes a review date.
Example: “12 Feb: launch with card payments only; bank transfer moves to phase two. Ruled out: delaying launch for both. Why: bank transfer needs a compliance review we can’t finish before March. Owner: Priya.”
To start one, copy the free decision log template. For a lighter four-field method, see how founders keep a decision log.
What is a RAID log?
A RAID log is a project-management tool for tracking the four kinds of thing that most often knock a project off course. It’s a living document: items are added, updated and closed throughout the project.
Risks
Something that might happen and would affect the project.
“Our lead developer may be unavailable in April.”
Assumptions
Something the plan treats as true without proof yet.
“The client will provide content by 1 March.”
Issues
A problem that is already happening.
“The test environment has been down since Monday.”
Dependencies
Something the project needs from another team, task or organisation.
“Go-live depends on the bank enabling the new account.”
Example: one product launch, five items
Fictional example. Details are invented.
A small consumer brand is three weeks from launch. In one status meeting, five things come up. Here’s where each one belongs:
- Decision log
“We will move the launch from 3 March to 17 March.”
A choice was made, with alternatives (cut scope, launch anyway) and a reason. Record who decided and why.
- RAID log: Risk
“The packaging supplier may not deliver before 10 March.”
It hasn't happened. It might. It needs a likelihood, an impact, an owner and a mitigation.
- RAID log: Issue
“The payment integration failed in staging on Tuesday.”
It has already happened and is blocking work. It needs an owner and a resolution date.
- RAID log: Dependency
“Launch can't go ahead until the regulator approves the label wording.”
Progress depends on someone outside the team. Track who, what and when.
- RAID log: Assumption
“Retail partners will keep their current shelf allocation.”
The plan relies on it being true, but nobody has confirmed it. Note it and check it.
Notice how they connect. The supplier risk and the failed integration are why the launch moved. The decision log entry should say so: “Delay to 17 March. Why: payment integration issue (RAID I-04) and supplier risk (RAID R-07).” Six months later, that one line explains the date.
When should you use each?
- Use a decision log when people will later need to know why something was done: pricing, scope cuts, supplier choices, hiring, anything that was argued about.
- Use a RAID log when a project has enough moving parts that uncertainty needs active management: several teams, outside suppliers, fixed deadlines.
- Use both on most projects longer than a few weeks. The RAID log drives the weekly conversation; the decision log keeps the outcomes of those conversations.
- Use a single RAID log if your organisation’s version already includes decisions (Risks, Actions, Issues, Decisions). Don’t keep the same information in two places.
Decision logs get confused with other records too. See decision log vs change log and decision log vs ADR.
Where Memoraxis fits
Both logs only hold what somebody wrote down. The discussion behind a decision (the email thread where the supplier warned you, the meeting where the date moved) usually lives in inboxes and calendars.
Memoraxis connects supported email, calendar and document sources, along with notes you add, into a business memory. You can then ask “when did we decide to move the launch, and why?” and see the conversations behind it.
Questions
- What is the main difference between a decision log and a RAID log?
- A decision log records choices that have been made, with the reasoning and the owner. A RAID log tracks what could go wrong or is going wrong (risks, assumptions, issues and dependencies) so it can be managed. One is a record of the past; the other is a working list of what is still uncertain.
- Does a RAID log include decisions?
- Sometimes. In the most common version RAID stands for Risks, Assumptions, Issues and Dependencies, with no decisions. Some organisations use Risks, Actions, Issues and Decisions instead, and then decisions are a section of the RAID log. Check which version your organisation uses before starting a separate decision log.
- Can a project have both?
- Yes, and most mid-sized projects do. The two link naturally: resolving a risk or issue often requires a decision, and the decision log entry can reference the RAID item that prompted it.
- Who maintains a RAID log?
- Usually the project manager, who reviews it with the team in regular status meetings. Each individual risk, issue or dependency should still have its own named owner responsible for acting on it.
- What should a decision log contain?
- At minimum: the date, the decision in one sentence, the reason, and who made it. Recording what was ruled out is the most useful addition, because it's the part nobody can reconstruct later. Status and review date help on longer projects.